1 11 pts Your Company's standards call for 1.5 hours per unit. The company planned to produce 900 units during May. However, 875 units were
1 11 pts Your Company's standards call for 1.5 hours per unit. The company planned to produce 900 units during May. However, 875 units were produced. The company worked 1,200 direct labor- hours. What are the standard hours (SQ) allowed for May production? O 1,350 1,313 1,800 875