1 3 . A company is to manufacture 2 0 0 parts per set up and that the job calls for 6 set ups. Calculate

13. A company is to manufacture 200 parts per set up and that the job calls for 6 set ups. Calculate the cost of production using the following data:
Machining time =24 minutes per component
Non-machining time =16 minutes per component
Tool sharpening =2 minutes per component
Set up time =80 minutes per set up
Gauging and inspection: 16 seconds and 8 checks per component
Tool life =12 hours
Direct labour cost = Rs.3 per hour.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Creating Value Along the Supply Chain

Authors: Roberta S. Russell, Bernard W. Taylor

7th Edition

9781118139523, 0470525908, 1118139526, 978-0470525906

More Books

Students also viewed these General Management questions

Question

Week 3: Moment of force: scalar formulation...explain it

Answered: 1 week ago