Question

1 Approved Answer

1 4 . 9 Refer again to Problems 1 4 . 5 and 1 4 . 7 . In addition to 1 0 0 units

14.9Refer again to Problems 14.5 and 14.7. In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week 8. Modify the net requirements plan to reflect these changes. [PX]