1 4 . The estimated variance for an activity with a most likely time ( m ) equal to 1 2 weeks, an optimistic time

14. The estimated variance for an activity with a most likely time (m) equal to 12 weeks, an optimistic time (a) equal to 9 weeks, and a pessimistic time (b) equal to 18 weeks is
a)3.75 weeks.
b)1.50 weeks.
c)5.25 weeks.
d)2.25 weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions