1 7 . A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C
A project consists of the following four activities with activity times in days:
Activity
Predecessor
Time
A
B
A
C
A
D
BC
Table YY
Using Table YY the amount of slack associated with activity C is
a days.
b days.
c days.
d day.