1 7 . A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C

17. A project consists of the following four activities with activity times in days:
Activity
Predecessor
Time
A
6
B
A
5
C
A
4
D
B,C
8
Table YY
Using Table YY, the amount of slack associated with activity C is
a)4 days.
b)3 days.
c)2 days.
d)1 day.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions