1. A contractor has a project that involves the construction of a large fill for a parking lot. After detailed analysis of the task, the

1. A contractor has a project that involves the construction of a large fill for a parking lot. After detailed analysis of the task, the contractor selected an equipment fleet of three scrapers, one crawler tractor to push load the scrapers, one grader to spread the fill material and grade the surface, and one compactor to compact the loose fill material dumped by the scrapers. The contractor determined the following cost data from historical records:

After analysis of the working conditions and the haul distance for the scrapers, the contractor determined that the productivity of the combined equipment fleet will be about 600 cubic yards per hour. What do you estimate the unit cost per cubic yard to construct the fill for the parking lot to be?image text in transcribed

Equipment Ownership Operating Cost Labor Cost (Less Labor Cost) (Operator) Cost $20.00 Crawler Tractor $15.00 Grader$10.00 $12.00 $65.00 $38.00 $18.00 $24.00 $28.00 $28.00 $28.00 $26.00 Scraper Compactor

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

World Finance Since 1914

Authors: Paul Einzig

1st Edition

0415539471, 978-0415539470

More Books

Students also viewed these Finance questions

Question

1. Why is reversing the right foots motion so hard?

Answered: 1 week ago

Question

Apply your own composing style to personalize your messages.

Answered: 1 week ago

Question

Format memos and e-mail properly.

Answered: 1 week ago