1. A loader has a full-bucket capacity of 10 yd3, and the average time required to place one bucketload of soil into a truck
1. A loader has a full-bucket capacity of 10 yd3, and the average time required to place one bucketload of soil into a truck is 1 min. The loader is supported by four trucks with a volume of 50 yd3 each and a cycle time of 12 min plus the time to load the truck. The ideal productivity (yd3/hr) of this system is most nearly?.