. 1 ) A network consists of the activities in the following list. Times are given in weeks. PrecedingTimeA - - 7 B - -

.1) A network consists of the activities in the following list. Times are given in weeks. PrecedingTimeA--7B--15CA3DA, B9EC12FD6 a. Draw the network diagram. b. Calculate the ES, EF ,LS, LF,c. Calculate the amount of Slack . What is project completion time? e. If activity C was delayed by six time units, what would happen to the project duration .

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions