1 . A project consists of the activities in the following list. ( 1 5 points ) Activity Immediate Predecessor ( s ) Time (

1. A project consists of the activities in the following list.
(15 points)
Activity Immediate Predecessor(s) Time (Days)
A --3
B A 4
C A 6
D B 6
E B 4
F C 4
G D 6
H E, F 8
a. Draw the AON (activity on node) project network diagram.
b. Calculate ES, EF, LS, LF, and Slack for each activity using the project activity nodes on the AON project network diagram.
c. What is the project completion time?
Identify the critical pathA project consists of the activities in the following list.
a. Draw the AON (activity on node) project network diagram.
b. Calculate ES, EF, LS, LF, and Slack for each activity using the project activity nodes on the
AON project network diagram.
c. What is the project completion time?
d. Identify the critical path
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions