1 . A project consists of the activities in the following list. ( 1 5 points ) Activity Immediate Predecessor ( s ) Time (
A project consists of the activities in the following list.
points
Activity Immediate Predecessors Time Days
A
B A
C A
D B
E B
F C
G D
H E F
a Draw the AON activity on node project network diagram.
b Calculate ES EF LS LF and Slack for each activity using the project activity nodes on the AON project network diagram.
c What is the project completion time?
Identify the critical pathA project consists of the activities in the following list.
a Draw the AON activity on node project network diagram.
b Calculate ES EF LS LF and Slack for each activity using the project activity nodes on the
AON project network diagram.
c What is the project completion time?
d Identify the critical path
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started