#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to

#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective?

#2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective?

#3. The following project is at the end of its sixth week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations.

Activity

Predecessors

Duration (wks)

Budget ($)

Actual Cost ($)

% Complete

a

-

2

300

400

100

b

-

3

200

180

100

c

a

2

250

300

100

d

a

5

600

400

20

e

b,c

4

400

200

20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions