1. A project manager has been assigned a software development project that is still in the early initiation phase with an unapproved charter . The
1. A project manager has been assigned a software development project that is still in the early initiation phase with an unapproved charter . The project sponsor has asked the project manager to review the draft scope statement and provide feedback . The project scope statement contains the following items
Scope description Scope exclusions Project assumptions Deliverables list Identified constrains Which of the following sections should be added? a. Acceptance criteria b. Detailed team assignments c. Wrist register d. Project schedule
2. Which of the following is a component of the project resource management? a. Identifying bench resources b. Managing resource cost c. Sharing inter project resources d. Avoiding resource constraints
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started