1. A project you work on has a budgeted cost of $1,20,000. You have 1 year to complete the project. One month has passed and
1. A project you work on has a budgeted cost of $1,20,000. You have 1 year to complete the project. One month has passed and only 15% of the project was completed instead of the planned completion of 20%. The expenses were found to be $150,000. a. Is the project over budget? Explain. b. Is the behind schedule? Explain. c. Calculate the estimate time to complete the project