1. Complete the following MRP time-phased record: a) Pizza Week 1 2 3 4 5 6 7 Gross Requirements 10 38 25 39 41 20

image text in transcribed
1. Complete the following MRP time-phased record: a) Pizza Week 1 2 3 4 5 6 7 Gross Requirements 10 38 25 39 41 20 43 25 Scheduled Receipts 72 Projected Available Balance 36 Planned Order Release Q = 50, LT = 2, SS = 5 The following events occurred during week 1: - Actual demand during week 1 was only 5 units - A cycle count of on-hand units showed 43 units at the start of week 1 - Marketing forecasted that 36 Pizza would be required in week 9 Update the record below after rolling through time. Pizza Week 2 C 7 9 Gross Requirements 25 39 20 43 25 Scheduled Receipts 12 Projected Available Balance Planned Order Release Q = 50, LT = 2, SS = 5

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

What advice would you give Lucille and Ann?

Answered: 1 week ago

Question

Explain exothermic and endothermic reactions with examples

Answered: 1 week ago

Question

Write a short note on rancidity and corrosiveness.

Answered: 1 week ago