1. Consider projects Alpha and Beta: Project Co C1 C2 Alpha -10,000 +6,000 +6,000 Beta -30,000 +18,000 +21,000 The opportunity cost is 9%. If Alpha
1. Consider projects Alpha and Beta: Project Co C1 C2 Alpha -10,000 +6,000 +6,000 Beta -30,000 +18,000 +21,000 The opportunity cost is 9%. If Alpha and Beta are mutually exclusive, what should you do? Choose both Alpha and Beta because the IRRs are greater than the cost of capital. Choose Beta because the incremental IRR is 10%. Choose Beta because the IRR is highest. Choose Beta because the incremental IRR is 21.65%. Choose Alpha because the IRR is highest