Question

1 Approved Answer

1 . construct a PERT network from the image, ( make sure you have the correct network before proceeding to the next sections ) 2

1.construct a PERT network from the image,(make sure you have the correct network before proceeding to the next sections)
2.by using ES, EF, LF, LS,find the slack of each activity and the critical path
3.find the completion time and the standard deviation for the project - round off the standard deviation to the nearest hundredth: two decimal places
4.what is the completion time at 99% confidence level
5.what is the likelihood of this project being completed in more than 14 days
6.between 11 and 13 days?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contemporary Issues In Strategic Management

Authors: Paul Phillips (Author) Luiz Moutinho (Author)

1st Edition

1138939641, 978-1138939646

More Books

Students also viewed these General Management questions

Question

=+b. Assuming you are currently charging $55 per table set,

Answered: 1 week ago

Question

Please explain the Constant Growth Stock Valuation (CGSV) formula.

Answered: 1 week ago