Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1) Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date:

1) Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date: 10 days

1.1) Perform the following analyses of the project based on the data given above. a. Cost Variance b. Schedule Variance

1.2) Plot an S-Curve and show CV and SV on it. professional quality work

1.3) Interpret results to explain the project status

2)Explain the purpose of a Control Chart being as detailed as possible with words and use illustrations as well to explained it better

3)Please explain why large initial separations on the EV S-Curve between the lines for ACWP and BCWP with BCWP above the ACWP may be an indicator of excessive front loading. Use detailed words and explanations and illustrations to explain it

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions

Question

Identify the major phases of the training and HRD process

Answered: 1 week ago