1. Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 17,000 toy action figures to be manufactured in June
1.
Direct Materials and Direct Labor Variances
At the beginning of June, Kimber Toy Company budgeted 17,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows:
Direct materials | $12,750 |
Direct labor | 9,180 |
Total | $21,930 |
The standard materials price is $0.50 per pound. The standard direct labor rate is $9.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows:
Actual direct materials | $12,000 |
Actual direct labor | 8,600 |
Total | $20,600 |
There were no direct materials price or direct labor rate variances for June. In addition, assume no changes in the direct materials inventory balances in June. Kimber Toy Company actually produced 15,500 units during June.
Determine the direct materials quantity and direct labor time variances. Round your per unit computations to two decimal places, if required. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Direct materials quantity variance | $ | |
Direct labor time variance | $ |
2.
Factory Overhead Cost Variances
The following data relate to factory overhead cost for the production of 4,000 computers:
Actual: | Variable factory overhead | $65,000 |
Fixed factory overhead | 25,500 | |
Standard: | 4,000 hrs. at $21 | 84,000 |
If productive capacity of 100% was 6,000 hours and the total factory overhead cost budgeted at the level of 4,000 standard hours was $92,500, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $4.25 per hour. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
Variance | Amount | Favorable/Unfavorable |
Variable factory overhead controllable variance | $ | Favorable |
Fixed factory overhead volume variance | Unfavorable | |
Total factory overhead cost variance | $ | Unfavorable |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started