Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1. Draw a Project Network and Determine the Critical Path (Show complete diagram) 2. Determine the one best activity to crash by adding more labor

1. Draw a Project Network and Determine the Critical Path (Show complete diagram)

2. Determine the one best activity to crash by adding more labor to complete the website in 15 days. (Show complete crashed project network diagram)

How many days can they delay information gathering until it lengthens the overall completion time for the website?

Please use this diagram to draw a diagram.

image text in transcribedimage text in transcribed
A 1.4 D 71 10 G 14 18 AES | EF O 1 4 37 10 2 141 18 + LS LF start ( 0 ) B 4 17 , C 7 1 10 E10 14 > F10/13 H 171 19- -Finish 34 / 7 2 7/10 610/ 14 310/ 13 2 17/1 19 ( 15 ) critical path: 2 . If we crash activity D.Immediate Activity Description Predecessor Time (Days) Information A 2 Gathering B Planning 3 C Design B 2 Content Writing D 3 and A.C Assembly F Coding C,D 6 Website F E 3 Testing Website G E 2 Review H Launch F.G 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern, Jill Gold

12th Edition

ISBN: 0367647893, 978-0367647896

More Books

Students also viewed these General Management questions