Answered step by step
Verified Expert Solution
Question
1 Approved Answer
1) Fail Ap Time Activity A Immediate Predecessor 2 5 B 1 C 10 D E B A, D 3 6 F G What
1) Fail Ap Time Activity A Immediate Predecessor 2 5 B 1 C 10 D E B A, D 3 6 F G What is the project duration time and what are the slack times of the activities? C E, F 8 92 2) Activity A Immediate Predecessor Time 524555235 B C DEFG H 1 A A B B C E, F D G, H What is the project duration time and what are the slack times of the activities? 3) Activity Immediate Optimistic Most Predecessor Time Likely Time Pessimistic Expected Variance Crash Time Crash Cost Time Time A 1 2 3 B 2 3 4 CDEFGH A 1 2 3 A, B 2 4 6 C 1 4 7 C 1 2 9 1222 $350/week $350/week $500/week $200/week D, E 3 4 11 4 $600/week F, G 1 2 3 What is the project duration time? What is the probability of completing the project in 16 weeks or less? What is the least cost of reducing the project duration by 3 weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started