1 . Given the project information below, answer the following questions: Activity Predecessor Optimistic Time ( a ) Most Likely Time ( m ) Pessimistic
Given the project information below, answer the following questions:
Activity Predecessor Optimistic Time a Most Likely Time m Pessimistic Time b Expected Time Te Variance
A None
B None
C A
D A B
E CD
Question CQ:
Using PERT method and based on expected time Te for each activity, determine the expected project duration rounded to whole numbers
CQ is based on the same information as presented for CQ
Given the project information below, answer the following questions:
Activity Predecessor OptimisticTime a MostLikely Time m PessimisticTime b ExpectedTime Te Variance
A None
B None
C A
D A B
E CD
Question CQ:
What is the probability of completing the project in periods? Fill a decimal value in the blank below Note: rounded to decimals
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started