Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1. Imagine that you were asked to prepare a monthly project status report (similar to the one shown below) for your group project (execution phase).

image text in transcribed
image text in transcribed
1. Imagine that you were asked to prepare a monthly project status report (similar to the one shown below) for your group project (execution phase). Prepare a similar type of report to be discussed in the next board meeting. Hint: You can choose the same values as described in the example below. Project number: 163 Project manager: Connor Gage Project priority now: 4 Status as of: April 1, 2007 Earned value figures: PV EV AC SV CV BAC 588,240 566,064 596,800 - 22,176 -30,736 1,051,200 EAC VAC EAC, CPI PCIB PCIC 1,090,640 -39,440 1,107,469 .95 538 .547 Project description: A computer-controlled conveyor belt that will move and position items on the belt with accuracy of less than one millimeter. Status summary: The project is approximately 25 days behind schedule. The project has a cost variance of ($30,736). Explanations: The schedule variance has moved from noncritical activities to those on the criti- cal path. Integration first phase, scheduled to start 3/26, is now expected to start 4/19, which means it is approximately 25 days behind schedule. This delay is traced to the loss of the second design team which made it impossible to start utilities documentation on 2/27 as planned. This loss illustrates the effect of losing valuable resources on the project. The cost variance to date is largely due to a design change that cost $21,000. Major changes since last report: The major change was loss of one design team to the project Total cost of approved design changes: $21,000. Most of this amount is attributed to the improved design of the serial 1/0 drivers. Projected cost at completion: EAC, is estimated to be $1,107,469. This represents an overrun of S56,269, given a CPI of .95. The CPI of.95 causes the forecast to be greater than the VAC - $39,440 Risk watch: Nothing suggests the risk level of any segments has changed. 1. Imagine that you were asked to prepare a monthly project status report (similar to the one shown below) for your group project (execution phase). Prepare a similar type of report to be discussed in the next board meeting. Hint: You can choose the same values as described in the example below. Project number: 163 Project manager: Connor Gage Project priority now: 4 Status as of: April 1, 2007 Earned value figures: PV EV AC SV CV BAC 588,240 566,064 596,800 - 22,176 -30,736 1,051,200 EAC VAC EAC, CPI PCIB PCIC 1,090,640 -39,440 1,107,469 .95 538 .547 Project description: A computer-controlled conveyor belt that will move and position items on the belt with accuracy of less than one millimeter. Status summary: The project is approximately 25 days behind schedule. The project has a cost variance of ($30,736). Explanations: The schedule variance has moved from noncritical activities to those on the criti- cal path. Integration first phase, scheduled to start 3/26, is now expected to start 4/19, which means it is approximately 25 days behind schedule. This delay is traced to the loss of the second design team which made it impossible to start utilities documentation on 2/27 as planned. This loss illustrates the effect of losing valuable resources on the project. The cost variance to date is largely due to a design change that cost $21,000. Major changes since last report: The major change was loss of one design team to the project Total cost of approved design changes: $21,000. Most of this amount is attributed to the improved design of the serial 1/0 drivers. Projected cost at completion: EAC, is estimated to be $1,107,469. This represents an overrun of S56,269, given a CPI of .95. The CPI of.95 causes the forecast to be greater than the VAC - $39,440 Risk watch: Nothing suggests the risk level of any segments has changed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Practical Guide To Commercial And Industrial Energy Auditing

Authors: Mtijan M Kamara

1st Edition

1717257321, 978-1717257321

More Books

Students also viewed these Accounting questions

Question

assess the infl uence of national culture on the workplace

Answered: 1 week ago