1 Johnny is a Project Manager at PLC Inc. He is tasked to build two double bedroom apartments a month for the coming twelve months.
1 Johnny is a Project Manager at PLC Inc. He is tasked to build two double bedroom apartments a month for the coming twelve months. Each apartments costs a hundred million rands. At the beginning of the tenth month, he has constructed 20 apartments and he has determinded the Cost Performance Index to be 0.9091. Senior management asks Johnny the percentage of the project that is complete if the whole project was scheduled to take 12 months. What should he report? 75 67 83 88 None of these