Question

1 Approved Answer

(1 point) Chili Palmer, a project office analyst at Jimbo's Java & Jerk, recently learned that it's possible to compress a project. The table below

(1 point) Chili Palmer, a project office analyst at Jimbo's Java & Jerk, recently learned that it's possible to compress a project. The table below provides the details for a new project including tasks, precedence relations, marginal compression costs, and maximum compression limits. The indirect and overhead cost rate is $145. Chili must develop a project schedule and would like to consider more than just the standard CPM schedule.

Because he has little experience with optimization, Chili would like you to formulate and solve the mathematical program(s) required to answer the questions below.

Note: Round all answers to 3 decimal places. When entering compression strategies, remember to include values for starting and ending tasks and enter your answer as a vector (e.g. ).

image text in transcribed Minimum Makespan Schedule Cost: Minimum Makespan Schedule \% Makespan Reduction (compared to CPM): CPM Makespan: TCTO % Cost reduction: Minimum Makespan Schedule \% Cost reduction (compared to CPM): TCTO Compression Strategy: Minimum Makespan Compression Strategy: id: 6740

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions