1 points Save An As a PM, you decided that due to the lack of special skills in your project team, the development of a
1 points Save An As a PM, you decided that due to the lack of special skills in your project team, the development of a specific part of the project is under high risk. Thus, you got the approval from the project sponsor to outsource it. This is an example of which risk response strategy? O A. Risk avoidance O B. Risk mitigation O C. Risk acceptance O D. Risk transfer