2. The production line of product X is described below. 504 units of product X must be produced daily with production time being 7 hours per day. Design a line that minimized the number of workstations based on the cycle time and the precedence of the tasks.
Task | Task Time (Seconds) | Immediate predecessor |
A | 45 | |
B | 11 | A |
C | 9 | B |
D | 50 | |
E | 26 | D |
F | 11 | E |
G | 12 | C |
H | 10 | C |
I | 9 | F,G,H |
J | 10 | I |
a. Draw a precedence diagram
b. Calculate cycle time.
c. Calculate the minimum number of workstations.
d. Balance the assembly line using maximum number of followers, in case of a tie use highest positional weight.
e. Calculate Efficiency of the line.
f. Calculate idle time in seconds.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started