Answered step by step
Verified Expert Solution
Question
1 Approved Answer
1. Project Captain George Task Duration Predecessor(s) Relationship Task Description Days P Task P 2 START FS Q Task Q 3 START FS+7 R Task
1. Project Captain George Task Duration Predecessor(s) Relationship Task Description Days P Task P 2 START FS Q Task Q 3 START FS+7 R Task R START FS+2 D Task D 6 P FF+7 A Task A 9 Q FS B Task B 8 R FS-2 G Task G 14 A, D A(SS+7), D(FS+5) H Task H 3 A SF+10 Task I 2 B, G, H FS END FSHints: you will have to develop a network diagram and using Day 1 to perform CPM 1. The project duration is Q; days 2. the critical path activity names between start and end are e; . Each name is separated by a dash. 3. The ESD of activity H is day a, 4. The LSD of activity A is day a, 5. The LSD of activity B is day a, 6. The ESD of activity G is day Q; 7'. The management will allow 35 days for the project to complete, the float is y, 8. Will the project complete in 33 days? The answer is l l v
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started