1. Question 1 What happens during a project closing? Select all that apply. 1 point The customer identifies new deliverables and ongoing task work. The
1.
Question 1
What happens during a project closing? Select all that apply.
1 point
The customer identifies new deliverables and ongoing task work.
The project manager and team confirms all project tasks are complete.
The team executes remaining project management processes, such as procedural or administrative work.
The team obtains formal recognition from key stakeholders that the project is complete.
2.
Question 2
What steps should a project manager take to make sure a project is closed? Select all that apply.
1 point
Confirm all tasks and work are complete
Spend any remaining funds in the project's budget
Ensure all agreed upon project management processes are complete
Get formal recognition from stakeholders that the project is done
3.
Question 3
Consider the following scenario:
The project manager reviews documentation for the project, including the statement of work and RACI chart. The project manager closes the vendor contract, submits all payments, and retrieves all final deliverables from contracted workers. They send an email communication to ensure all stakeholders are aware that the project is ending. Finally, the project manager finishes up the project by gathering final feedback and conducting closing surveys.
What step of the closing process did the project manager skip in this scenario?
1 point
Conduct administrative closure of the procurement process
Complete any necessary follow-up work, such as gathering data and information
Put together closing documentation, such as creating closeout reports
Refer to documentation created earlier in the project
4.
Question 4
What are the main purposes of the project closeout report? Select all that apply.
1 point
Provide an evaluation of the quality of work
Celebrate the team's success with a formal congratulations
Review the project's performance in respect to budget and schedule
Document what the team did, how they did it, and what they delivered
5.
Question 5
What is the purpose of the impact report?
1 point
Protect the scope of the project by properly communicating project issues
Demonstrate how the project went and discuss the impact of its product or service
Determine if the project needs a small closing process at the end of each milestone
Review the project with team members to discuss the details of the project
6.
Question 6
Consider the following scenario:
The project manager needs to include several sections in the closeout report for the Janco car company's new car series launch. First, the project manager completes the executive summary, describing the project process and purpose. Second, they note the key accomplishments like meeting the launch's objectives and highlighting the team's impact on the project. Third, they identify open items like what the team didn't complete, and add improvement ideas for similar, future projects. Fourth, they detail the next steps for follow-up projects. Fifth, they list the launch schedule with project milestones, project on-track status, and setbacks. And sixth, they list the project resources like the original project plan, stakeholder communications, and documents such as user manuals on how to unload cars from delivery trucks.
Which item is the project manager missing in their closeout report?
1 point
Key accomplishments
Open items
Lessons learned
Next steps
7.
Question 7
What meeting can you hold with your team to get feedback on the successes and failures of a project you are closing?
1 point
A retrospective meeting
An an impact report meeting
A performance review
A team celebration
8.
Question 8
Due to an inadequate handoff, the final deliverable never made it to the customer. What type of project does this describe?
1 point
Unapproved
Abandoned
Unwritten
Never-ending
9.
Question 9
Which closeout report section includes topics such as things the team didn't get to work on and ideas for changes if they had the time?
1 point
Key accomplishments
Executive summary
Lessons learned
Open items
10.
Question 10
A project manager is closing out a project. How can they encourage continuous growth in their team? Select all that apply.
1 point
Reallocate resources
Archive documents
Recognize contributions
Celebrate accomplishments
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started