Question
1 Approved Answer
1 . Question 1 What is project tracking? 1 point A method for assessing project successes and areas for improvement. A method for responding to
Question
What is project tracking?
point
A method for assessing project successes and areas for improvement.
A method for responding to project risks.
A method for following the progress of a project's activities.
A method for reaching agreement among stakeholders on project scope.
Question
What should project managers track to ensure the team meets deadlines?
point
Track tasks as they progress and as the project approaches key milestones.
Track stakeholder engagement to ensure they are aligned on project goals.
Track costs to avoid over or underspending on project activities.
Track project successes and celebrate achievements with the team.
Question
A stakeholder wants you to create a chart with a granular breakdown of each task and the time remaining to complete the tasks. What type of chart can you present to them?
point
Burndown chart
Gantt chart
Project status report
Roadmap
Question
How does a roadmap differ from a Gantt chart?
point
A roadmap is useful for large projects with many dependencies; a Gantt chart tracks big milestones and includes a highlevel project overview.
A roadmap measures time against the amount of work completed and remaining; a Gantt chart is useful for large projects with many dependencies.
A roadmap is useful for large projects with many dependencies; a Gantt chart measures time against the amount of work completed and remaining.
A roadmap tracks big milestones and includes a highlevel project overview; a Gantt chart is useful for large projects with many dependencies.
Question
Imagine an auto manufacturer has a project to build a new model of car. The project manager learns there is a delay of a key shipment of parts. Which of the triple constraints does this change impact the most?
point
Scope
Timeline
Budget
Question
Which of the following items should a project manager include in a change request form for a project team? Select all that apply.
point
Retrospective summary
Teams involved
Original project proposal
Project name
Question
A team starts a new project to launch a website. The first task is to create the designs of the webpage. The second task is to develop the web pages based on the designs. What type of dependency does this indicate?
point
Mandatory dependency
Discretionary dependency
Internal dependency
External dependency
Question
You brainstorm with your team members to identify and list the events that might delay the project. What type of document are you creating in this scenario?
point
Task List
Impact Matrix
Risk register
Risk Matrix
Question
What should you do in an escalation email? Select all that apply.
point
State your connection to the project.
Be serious and assert authority.
Explain the problem.
Make a request.
Question
Two team members in your project cannot seem to come to an agreement on a new design feature. What common issue does this represent in project management?
point
Trench wars
Risk appetite
Tradeoff agreement
Bad compromises
Question
As a project manager, youre implementing the ROAM technique for a new risk. You assign the risk to a team member so they can resolve it and monitor it to completion. Which ROAM action did you take?
point
Resolved
Owned
Accepted
Mitigated
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started