Question
1. Question1 Referring to Drucker (2006), which of the following describes a BAD action plan? 1 point It should be a basis for executive time
1.
Question1
Referring to Drucker (2006), which of the following describes a BAD action plan?
1 point
It should be a basis for executive time management, anticipating a likely scenario for time spend in the project
It provides a system for checking against expectations, adjusting the course of action as the plan is executed
It should have the best estimate for all tasks in order to anticipate what needs to be done, but it should be flexible as the plan is executed and new pieces of information arise
It should provide a straight commitment from the management, both for the tasks to be executed and target of the plan, leaving no room for change or adaptation
2.
Question2
A Work Breakdown Structure is used to visualize and break a project into:
1 point
Work packages
Organizational hierarchy
A critical path
Time units
3.
Question3
When planning a festival, the program cannot be printed before the key artists are committed. Which precedence relationship best describes the relationship between "get artists' commitment" and "print program"?
1 point
Start-to-Start
Start-to-Finish
Finish-to-Finish
Finish-to-Start
4.
Question4
Figure 1: Design/Dependency Structure Matrix for Project X
According to the pictured Design/Dependency Structure Matrix, Task 4 is dependent on which tasks?
1 point
Task 2 only
Tasks 2 and 3
Task 5 only
Tasks 5 and 6
5.
Question5
Figure 2: Network Diagram for Project X
What is the earliest possible completion time for this project?
1 point
11 weeks
12 weeks
13 weeks
14 weeks
6.
Question6
Figure 2: Network Diagram for Project X
Which tasks will be critical if the Sales task takes 7 weeks instead of 6?
1 point
Creative, Fundraising, and HR
Strategy, Marketing, and Finance
Creative, Sales, and Finance/HR
Creative, Sales, and Finance
7.
Question7
Figure 2: Network Diagram for Project X
If the IT task takes 6 weeks instead of 5, what will be the earliest possible completion time for this project?
1 point
14 weeks
15 weeks
16 weeks
17 weeks
8.
Question8
What is the main goal of crashing a project activity?
1 point
To create less slack in the project
To create less risk associated with the project
To eliminate the emergence of a new critical path
To increase the duration of project activities
9.
Question9
Which of the following describes an "as soon as possible" schedule?
1 point
Delays the committment of costs and resources
Constrained by time so compromise costs early on to provide slack time
Benefits on costs, but downside on time
Constrained by costs so incur them immediately
10.
Question10
The backward pass is used to determine the Latest Start Time (LST) and Latest Finish Time (LFT) of tasks. The LFT of a task is the _____ of the LST of all succeeding tasks.
1 point
Average
Minimum
Maximum
Sum
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started