Question

1 Approved Answer

1) Read the Cisco Metals scenario from Week 6. 2) Develop a timeline to describe the events that occurred. 3) Generate a list of 5

1) Read the "Cisco Metals" scenario from Week 6. 2) Develop a timeline to describe the events that occurred. 3) Generate a list of 5 'unknowns' or questions for which you want answers or further information to allow you to create a more comprehensive and detailed timeline. 4) Develop a process map using 'swimlanes' to describe the "as-is" process of interest for this case study.

Scenario - Cisco Metals On January 3, 2018, following the Christmas production shutdown, there was a 2 day delay in the start-up of a production line at Cisco Metals. Over the Christmas shutdown, there was repair work happening on the furnaces in the facility. Thirty coils were being replaced in one of the furnaces. The delay cost 2 days of production at about $7000 per day. There were also 14 additional people on each crew working around the clock because of the maintenance delay. This delay was due to the maintenance staff not having the grinding wheels needed to cut this particular coil from the furnace. The grinding wheels they had were #62 and they needed #62-2. Maintenance had put in a request 4 weeks ago and received the wheels a week later, but did not realize they had the incorrect grinding wheels until the job was started. The purchasing department substituted #62 wheels for the #62-2 wheels that were originally requested. They appeared to be the same wheel and the #62 wheels were $40 less than the #62-2 grinding wheels. Purchasing regularly substitutes a less expensive part if it provides the same function. In this case, the material was different between the two grinding wheels and had been selected specifically for cutting the alloy that had been used in the furnace coils. The #62 wheels cut much slower and kept breaking which was dangerous though no one had been injured. The delay came from the slow cutting time, work stoppage, and waiting for the original #62-2 wheels that were now being sent on an emergency basis.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Materials Science and Engineering An Integrated Approach

Authors: David G. Rethwisch

4th Edition

1118214226, 1118061608, 9781118214220, 978-1118061602

More Books

Students also viewed these Mechanical Engineering questions