Question
1. Sloan Corporation is considering new equipment. The equipment can be purchased from an overseas supplier for $3,180. The freight and installation costs for the
1. Sloan Corporation is considering new equipment. The equipment can be purchased from an overseas supplier for $3,180. The freight and installation costs for the equipment are $660. If purchased, annual repairs and maintenance are estimated to be $430 per year over the four-year useful life of the equipment. Alternatively, Sloan can lease the equipment from a domestic supplier for $1,540 per year for four years, with no additional costs.
Prepare a differential analysis dated December 3, to determine whether Sloan should lease (Alternative 1) or purchase (Alternative 2) the machine. (Hint: This is a "lease or buy" decision, which must be analyzed from the perspective of the machine user, as opposed to the machine owner.) If an amount is zero, enter "0". Use a minus sign to indicate a loss.
Differential Analysis | |||
Lease Equipment (Alt. 1) or Buy Equipment (Alt. 2) | |||
December 3 | |||
Lease Equipment (Alternative 1) | Buy Equipment (Alternative 2) | Differential Effect on Income (Alternative 2) | |
Revenues | $ | $ | $ |
Costs: | |||
Purchase price | $ | $ | $ |
Freight and installation | |||
Repair and maintenance (4 years) | |||
Lease (4 years) | |||
Income (loss) | $ | $ | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started