1. Tasks can occur sequentially or _______ and tasks should have ___________assigned to perform each task. (5 Points) a) simultaneously, a resource b) logically, workforce
1. Tasks can occur sequentially or _______ and tasks should have ___________assigned to perform each task. (5 Points)
a) simultaneously, a resource
b) logically, workforce
c) intermittently, material and equipment
2. The sequence of schedules is as follows: (5 Points)
a) contractual relationships, physical relations, managerial relationships
b) managerial relationships, contractual relationships, physical relations
c) physical relationships, contractual relationships, managerial relationships
3. A type of micro-schedule that provides a snapshot of a short period of time (two-week and three-week durations) in the schedule is called _____________________. (3 Points)
a) the look-ahead schedule
b) checklist
c) Linear schedule
d) Program review and evaluation
4. The duration of the task in measured in ___________. (2 Points)
a) weeks and months
b) workdays
c) calendar days
5. In some situations, an activity cannot start until a certain time after the end of its predecessor and the waiting period, commonly known as a __________. (3 Points)
a) Lag
b) Lead
c) logical relationship
d) dependency
6. CPM scheduling approach is also called LineofBalance scheduling. (2 Points)
a) True
b) False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started