Question
1. The following information is available for the month of April from the First department of the Armque Corporation: Units Work in process, April 1
1. The following information is available for the month of April from the First department of the Armque Corporation:
| Units |
Work in process, April 1 (50% complete) | 90,000 |
Started in April | 250,000 |
Transferred to Second Department in April | 280,000 |
Work in process, April 30 (40% complete) | 60,000 |
Materials are added in the beginning of the process in the First department. Using the average cost method, what are the equivalent units of production for the month of April?
Materials | Conversion |
a. | 310,000 250,000 |
b. | 250,000 295,000 |
c. | 340,000 316,000 |
d. | 340,000 304,000 |
2. The following information is available for the month of August from the First department of the Twigg Corporation:
| Units |
Work in process, August 1 (60% complete) | 50,000 |
Started in August | 190,000 |
Work in process, August 30 (40% complete) | 80,000 |
Materials are added in the beginning of the process in the First department. Using the average cost method, what are the equivalent units of production for the month of August?
Materials | Conversion |
a. | 192,000 240,000 |
b. | 190,000 192,000 |
c. | 240,000 208,000 |
d. | 240,000 192,000 |
3. Information concerning Department A of Ali Company for the month of June is as follows:
|
Units | Materials Costs |
| ||
Work in process, beginning of month | 20,000 | $14,550 |
Started in June | 85,000 | $66,300 |
Units completed | 90,000 |
|
Work in process, end of month | 15,000 |
|
All materials are added at the beginning of the process. Using the average cost method, the cost (rounded to two places) per equivalent unit for materials for June is:
a. | $0.74. |
b. | $0.90. |
c. | $0.77. |
d. | $0.78. |
4. Plemmon Company adds materials at the beginning of the process in the forming department, which is the first of two stages of its production cycle. Information concerning the materials used in the forming department in April follows:
|
Units | Materials Costs |
Work in process at April 1 | 15,000 | $ 8,000 |
Units started during April | 60,000 | $38,500 |
Units completed and transferred to next department during April |
65,000 |
|
Using the average cost method, what is the materials cost of the work in process at April 30 (rounded to nearest dollar)?
a. | $7,154 |
b. | $6,200 |
c. | $7,750 |
d. | $6,417 |
5. The following information is available for the month of April from the First department of the Armque Corporation:
| Units |
Work in process, April 1 (50% complete) | 90,000 |
Started in April | 250,000 |
Transferred to Second Department in April | 280,000 |
Work in process, April 30 (40% complete) | 60,000 |
Materials are added at the end of the process in the First department. Using the average cost method, what are the equivalent units of production for the month of April?
Materials | Conversion |
a. | 304,000 250,000 |
b. | 280,000 295,000 |
c. | 340,000 316,000 |
d. | 280,000 304,000 |
6. The following information is available for the month of August from the First department of the Twigg Corporation:
| Units |
Work in process, August 1 (60% complete) | 50,000 |
Started in August | 190,000 |
Work in process, August 30 (40% complete) | 80,000 |
Materials are added at the end of the process in the First department. Using the average cost method, what are the equivalent units of production for the month of August?
Materials | Conversion |
a. | 192,000 160,000 |
b. | 160,000 192,000 |
c. | 160,000 208,000 |
d. | 240,000 192,000 |
7. During June, Birch Bay Company's Department B equivalent unit product costs computed under the average cost method were as follows:
Materials | $2 |
Conversion | $3 |
Transferred-in | $5 |
Materials are introduced at the end of the process in Department B. There were 4,000 units (60 % complete as to conversion costs) in work in process at June 30. The total costs assigned to the June 30 work in process inventory should be:
a. | $20,000. |
b. | $24,800. |
c. | $27,200. |
d. | $35,200. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started