Question
1. The labor costs (cost of personnel) of a project are considered to be which of the following type of cost? Group of answer choices
1. The labor costs (cost of personnel) of a project are considered to be which of the following type of cost?
Group of answer choices
(G&A) overhead costs
direct project overhead costs
contingency cost
direct cost
Flag question: Question 2Question 21 pts
2. Given the following scenario, which type of estimating are you using?
You are painting your living room which is twice as large as your bedroom. Last year the cost to paint your bedroom was $200. You will be using the same type of paint for your living room so you estimate the cost to be $400.
Group of answer choices
parametric estimating
iterative estimating
top-down estimates
phase estimating
Flag question: Question 3Question 31 pts
3. In the traditional budget process, the project's value and associated budget determines the project's design.
Group of answer choices
True
False
Flag question: Question 4Question 41 pts
4. A typical contingency fund is _________ of the total budget but depends on the risks associated with the project.
Group of answer choices
1/3
25%
at least half
10% to 15%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started