Question
1 Approved Answer
1 . The resource expenditure of each lowest - level WBS activity is estimated. 2 . Resource effort ( duration and cost ) in monetary
The resource expenditure of each lowestlevel WBS activity is estimated.
Resource effort duration and cost in monetary terms is estimated for all the resources.
Costs for all the activities under the same WBS element at the next higher level are rolled up
This process is continued for all the WBS elements to determine the overall project estimate.