1. The task named 'Pour foundation' is estimated to take 10 days. The task type is the default task type. Hany is assigned to work
1. The task named 'Pour foundation' is estimated to take 10 days. The task type is the default task type. Hany is assigned to work 100% of his time for 80 hours. Change the work to 40 hours. What is the new duration?
2. Carole Poland has been hired to conduct qualitative risk analysis. The duration of the task is 7 days and the work is calculated as 56 hours. Carole believes the task will take 9 days to finish and the project manager agreed to allow her 9 days to finsh the work, but absolutely no more than 9 days. This is a ____________________ type of task. Change the required hours to 9 days. The new work recalculates to become ____________________.
3. Carole Poland has been given the responsibility of managing the project MS Project file. One of the project coordinators also works in a secondary role as a risk manager. They have different pay structures for each role. Carole would like to create an additional cost rate table for this resource. How can Carole accomplish this?
4. Justin Thomas would like to make adjustment to the Gantt chart view. Which of the following is NOT a selectable Gantt bar style name?
A) Automatic progress B) External tasks C) External milestones D) Manual progress
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started