1. The total efforts number in pm of a project was originally estimated at 60 pm and staffed with 6 workers. However after 5 months,
1. The total efforts number in pm of a project was originally estimated at 60 pm and staffed with 6 workers. However after 5 months, management discovered that the effort number was underestimated because the project was only 40% completed.
(Total efforts (in pm) = Number of persons x Duration in months)
- Compute the revised total efforts to reflect the actual progress in person-months (2 pts)
- If management wanted to complete the project within the planed schedule, how many more workers should be hired (3 pts)?
2. Microsoft Quality Development.
a. Briefly discuss the Daily/Nightly Build/Synchronization development process (3 pts).
_____________________________________________________________________________________
Who is the leader of the process? (2 pts)
______________________________________________________________________________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started