1. Valen Time Limit: 03:20:00 Submi This Question: 2 pts 36 of 50 (46 completo) This Test: 100 pts po Gwynnio Pio Company makes dessert ples for national fast food chains. Gwynnie Pie Company is considering using ABC costing and has the following activity cost pools and information available Activities Estimated Overhead Costs Estimated Activity Material handling measured by batches $253,000 1.840 batches Missing measured by batches $118,000 4,000 batches Packaging measured by units $74,000 1,850,000 units Maintenance measured by # of setups $15,000 260 setups Gwynnie Pie Company currently uses a plantwide overhead rate based on total estimated machine hours of 100,000 hours. Based on their estimates for ABC costing, what would the allocated cost for all overhead costs for Job 607 be based on the following information about the job: #of units in the job - 4,700 O A $1,023.00 OB. $1.080.69 C. $412.69 OD. $1,012.00 Click to select your answer 1:12 AM 1/21/2020 O Type here to search 8 8 THIS IS TUU ptsp Material handling measured by batches $253.000 1,840 batches Mixing measured by batches $118.000 4.000 batches Packaging measured by units $74,000 1,850,000 units Maintenance measured by # of setups $15.000 260 seps Gwynnie Pie Company currently uses a plantwide overhead rate based on total estimated machine hours of 100,000 hours. Based on their estimates for ABC costing, what would the located cost for all overhead costs for Job 607 be based on the following information about the job # of units in the job = 4,700 #of units in each batch = 940 #of setups required to complete the job = 1 # of machine hours = 220 O A $1,023.00 OB. $1.080.69 O C. $412.69 OD. $1,012.00 Click to select your answer 112 AM 200 Type here to search o RE B Esc 8 $ % 5 8 # 3 6 4. 2 U R