Question

1 Approved Answer

1) What data does the Integrated Program Management Report (IPMR) Format 3 detail? (IMAGE DESCRIPTION: IPMR Format 3 sample shows section 6, Performance Data, which

1) What data does the Integrated Program Management Report (IPMR) Format 3 detail?

(IMAGE DESCRIPTION: IPMR Format 3 sample shows section 6, Performance Data, which includes representative values for the PMB at the beginning and end of the period, authorized baseline changes, management reserve, and the total budget. Representative values for the PMB at the beginning and end of the period, and authorized baseline changes include: BCWS cumulative to date; BCWS for the reporting period; BCWS for a six period forecast; BCWS by quarter; the to complete value; undistributed budget; and total budget.)

A.) IPMR Format 3 details current and cumulative budgeted cost for work scheduled (BCWS)data for the current period, as well as cumulative budgeted cost for work performed (BCWP)for future reporting periods.

B.) IPMR Format 3 is limited to detailing only the current reporting period budgeted cost for work scheduled (BCWS)data.

C.) IPMR Format 3 details current budgeted cost for work scheduled (BCWS), cumulative BCWS data for the beginning and end of the current period, but it does not include any forecasted BCWS.

D.) IPMR Format 3 details current budgeted cost for work scheduled (BCWS), cumulative BCWS data for the beginning and end of the current period, and forecasted BCWS for future reporting periods.

image text in transcribed
Integrated Program Management Report, Format 3 6. Performance Data Budgeted Cost for Work Scheduled (BCWS) (Non-Cumulative) BCWS BCWS for Cumu Reporting lative Period to Date Undistr- ibuted Total Budget Budget Six Period Forecast Enter Specified Periods Nov Dec Jan Feb Mar Apr 03'15 04'15 Q1'16 0216 TC PMB (Beginning of 32.566.3 1.960.8 2,072.4 2,368.5 2,116.6 2.039.92.699.6 1,302.6 1,830.83,998.0 3,589.0 3,231.0 3,274.70.0 63,050.2 Period Baseline Changes Authorized During Reporting Period R-101 25.6 25.6 25.6 25.6 25.6 128.0 PMB (End of 34,527.1 Period 2,0724|2.3685|21422| 2.065.5|27252|1.328.2 | 1.8564|3998? 3.589.013231.0|3274.7| 0.0 63.178.21 1,598.7 64,776.9 Management Reserve Total

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

IS Audit And Control For Accountants

Authors: Mr Amir Manzoor

1st Edition

1493665006, 978-1493665006

More Books

Students also viewed these Accounting questions

Question

What has been your desire for leadership in CVS Health?

Answered: 1 week ago