1. What kind/type of visual data representation is most similar to the Gantt chart? a. bar chart b. scatter diagram c. bubble diagram d. tornado
1. What kind/type of visual data representation is most similar to the Gantt chart?
a. bar chart
b. scatter diagram
c. bubble diagram
d. tornado diagram
2. Whenever first exploring the time-cost trade-off of a project, ______ costs should be considered first along with direct resource costs.
A. overhead/indirect
B. penalty
C. bonus
D. discounting
3. As, from a technical perspective, ______ kind of estimate implies that the actual value for the variable, a task's work content for example, will occur with 100% probability, or that work content has zero variance (i.e., there are no deviations from the estimated value). A. deterministic
B. stochastic
C. parametric
D. optimistic
4.______ is a dependent task that logically comes after another task or tasks in a project schedule.
A. Successor
B. Precedence relations
C. Predecessor
D. Precedence constrains
5. Tasks that ______ is NOT an appropriate way of classifying a task for planning purposes.
A. deliver against project requirements
B. result in a positive financial outcome
C. manage risks associated with the project
D. manage project process
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started