1 . When multiple supplier or subcontractor quotes are received for the same work, what is the most important reason to review the quote before
When multiple supplier or subcontractor quotes are received for the same work, what is the most important reason to review the quote before considering their price? A Make sure they are putting your favorite superintendent or foreman on the job B They intend to take you out to lunch every Friday for the time they are on site C They have the proper scope of work included D They have the lowest bond rate