1. Which activities have slack in the following diagram? start B 3 E1 finish A4 C 2 D7 F2 a. A, C, D, F b.
1. Which activities have slack in the following diagram? start B 3 E1 finish A4 C 2 D7 F2 a. A, C, D, F b. B, E c. A, C, D, E d. B, D, E 2. What is the latest finish time for activity D in the following diagram? start B3 E 1 finish A4 C2 D7 F 2 a. 6 b. 13 c. 14 d. 15 3. What is the earliest start time for activity D in the following diagram? start B 3 E 1 finish A4 C2 D7 F2 a. 3 b.4 c. 6 d. 7 4. What are the immediate predecessors of activity D in this network? start B3 E1 finish A4 C2 D7 F2 a. A, B, C b. B, C c. E, F d. E, G, H
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started