Question
1) Which of the following is a Scrum ceremony? A) Sprint Backlog B) Sprint Retrospective C) Product Backlog D) Backlog Grooming Meeting 2) Which of
1) Which of the following is a Scrum ceremony?
A) Sprint Backlog B) Sprint Retrospective C) Product Backlog D) Backlog Grooming Meeting
2) Which of the following activities take place during project planning? Select all that apply.
A) Sprint planning meeting B) Creation of product backlog C) Creation of sprint backlog D) Creation of the product roadmap
3) The product owner is responsible for which of the following activities?
A) Managing the sprint backlog B) Facilitating the Daily Scrum C) Grooming the product backlog D) Funding the project
4) Which of the following is a Scrum artifact?
A) Product vision B) Release plan C) Increment/Product backlog D) Scrum board
5) Which Scrum ceremony takes place during sprint execution?
A) Daily Scrum B) Sprint Retrospective C) Sprint Planning Meeting D) Sprint Review
6) True or false: Within the same project, every sprint is the same length.
A) True B) False
7) The purpose of a sprint review is to ...
A) Determine the user stories that will be completed during a sprint.
B) Discuss what went well and what could be improved for future sprints.
C) Demonstrate and discuss the work completed during the sprint.
D) Provide status updates to keep the team coordinated during a sprint.
8) Which of the following are scrum rules? Select all that apply.
A) The daily scrum should not exceed 15 minutes.
B) Every sprint begins with a retrospective.
C) The sprint always ends with a sprint retrospective.
D) A sprint is no more than five weeks in duration.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started