Question
1. Which of the following is (are) true of the Precedence Diagramming Method (PDM)? a. It refers to a method for calculating schedule risk b.
1. Which of the following is (are) true of the Precedence Diagramming Method (PDM)?
a. It refers to a method for calculating schedule risk
b. It can be used to calculate activity duration
c. It can depict four types of dependencies
d. All of the above - Not correct
2. The dependency between activities A and B is a start-to-start: B cannot start until A has started. If the duration of A is 5 days and the duration of B is 7 days, how many days after A starts will A and B both be done? a. 12
b. 10 - No correct
c. 2
d. 7
3. Applying the learning curve when determining duration is an example of using
a. Analogous estimating
b. Parametric estimating
c. Bottom-up estimating - Not correct
d. Three-point estimating
4. The forward pass algorithm is used to
a. Determine the critical path
b. Estimate activity duration
c. Evaluate project risk - Not correct
d. Transition the project to the project sponsor
5. The fast tracking schedule compression technique usually
a. Vastly increases cost
b. Increases concurrency of activities
c. Results in unacceptable quality
d. Enables faster tracking of project progress - Not Correct
These are previously asked questions that were answered incorrectly.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started