1. Which of the following is (are) true of the Precedence Diagramming Method (PDM)? a. It refers to a method for calculating schedule risk b.

1. Which of the following is (are) true of the Precedence Diagramming Method (PDM)?

a. It refers to a method for calculating schedule risk

b. It can be used to calculate activity duration

c. It can depict four types of dependencies

d. All of the above - Not correct

2. The dependency between activities A and B is a start-to-start: B cannot start until A has started. If the duration of A is 5 days and the duration of B is 7 days, how many days after A starts will A and B both be done? a. 12

b. 10 - No correct

c. 2

d. 7

3. Applying the learning curve when determining duration is an example of using

a. Analogous estimating

b. Parametric estimating

c. Bottom-up estimating - Not correct

d. Three-point estimating

4. The forward pass algorithm is used to

a. Determine the critical path

b. Estimate activity duration

c. Evaluate project risk - Not correct

d. Transition the project to the project sponsor

5. The fast tracking schedule compression technique usually

a. Vastly increases cost

b. Increases concurrency of activities

c. Results in unacceptable quality

d. Enables faster tracking of project progress - Not Correct

These are previously asked questions that were answered incorrectly.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Beetons Book Of Household Management

Authors: Arlene Morriso

1st Edition

1721995153, 978-1721995158

More Books

Students also viewed these General Management questions

Question

Distinguish a project from a program, activity, and task?P-63

Answered: 1 week ago

Question

Define positive thinking and negative thinking. (pp. 170, 172)

Answered: 1 week ago

Question

=+vii. Bullet points to emphasize important ideas.

Answered: 1 week ago