Question
1) Wind and Water Energy Company hired Smith Construction Corporation to build a new building for its operation. Smith agreed to build the plant for
1) Wind and Water Energy Company hired Smith Construction Corporation to build a new building for its operation. Smith agreed to build the plant for $1,200,000, and Wind and Water Energy agreed to pay Smith $300,000 on January 1 and July 1 for two years, beginning July, 2006. Smith estimates that it will incur total costs of $950,000 to complete construction. The following details at December 31, 2006:
Costs incurred to date $400,000
Estimated costs to complete 550,000
Billings to date 300,000
Collections to date 300,000
Required:
1. Calculated the amount of income that Smith should recognize for 2006, using the percentage-of-completion method.
2) Sad Construction Company use the percentage-of-completion method when total Construction can be estimated. Sad is building an office building for Porter Company for $10,000,000 with the following details:
12/31/2004 12/31/2005 12/31/2006
Costs incurred to date $2,000,000 $3,500,000 $6,500,000
Estimated costs to complete 6,000,000 4,500,000 1,500,000
Billing to date 6,000,000 8,000,000 10,000,000
Collections to date 3,000,000 5,500,000 10,000,000
Required:
1. Prepared all journal entries for 2004 that Sad should make for this job.
2. Prepared all journal entries for 2005 that Sad should make for this job.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started