Question
1) You are a contractor, and the owner has asked you to choose an indemnity clause for his benefit. Which form of the clause provides
1) You are a contractor, and the owner has asked you to choose an indemnity clause for his benefit. Which form of the clause provides him/her the best protection?
a) broad form b) limited form c) intermediate form d) no form
2) What are the potential risks for the contractor related to a field change?
a) The owner may not pay for it risking litigation. b) The owner could be sued for a tort. d) The owner is open to a flow down clause. c) There are no risks the owner signed and agreed to the change.
3) The contractor notices that on the shop drawing returned by the architect, some steel columns have been changed from size 6 to size 7. What avenues does he have for payment?
a) a change order b) a field change c) waiver of consequential damages. d) liquidated change order
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started