Question

1 Approved Answer

1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9

1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.

What is the Schedule Variance (SV)?

Round your answer to 2 decimal places

2. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.

What is the Earned Value (EV)?

Round your answer to 2 decimal places.

3. You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have completed 14 of the 32 deliverbles (all of equal value). You have spent $28,000 of your original budget of $48,000.

What is the Earned Value (EV)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring The Hospitality Industry With Hospitality Interactive

Authors: John R Walker

2nd Edition

0132680475, 9780132680479

More Books

Students also viewed these General Management questions

Question

Is it tenure-track, tenured, or something other designation?

Answered: 1 week ago