1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9
1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Schedule Variance (SV)?
Round your answer to 2 decimal places
2. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Earned Value (EV)?
Round your answer to 2 decimal places.
3. You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have completed 14 of the 32 deliverbles (all of equal value). You have spent $28,000 of your original budget of $48,000.
What is the Earned Value (EV)?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started