1. You are providing a status for a 14-week project, which is scheduled to be 50 percent...
Question:
1. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Schedule Variance (SV)?
Round your answer to 2 decimal places
2. You are providing a status for a 14-week project, which is scheduled to be 50 percent complete at this time. You have completed 9 of the 16 deliverables in this project and spent $1200 of the total project cost of $1900.
What is the Earned Value (EV)?
Round your answer to 2 decimal places.
3. You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have completed 14 of the 32 deliverbles (all of equal value). You have spent $28,000 of your original budget of $48,000.
What is the Earned Value (EV)?