1) You have a project to install 50 solar panels on a roof. You estimate that you can install 5 panels a day, and thus

image text in transcribed
1) You have a project to install 50 solar panels on a roof. You estimate that you can install 5 panels a day, and thus it will take you 10 working days. The cost per installed solar panel, including material and labour is $2,250. You are at the end of Day 6, at 4pm and realize you have installed 20 panels and the cost spent so far is $35,000 a. What is the total cost of the project at the end? What percent of the work has been done? b. What is the planned value, earned value, actual cost, at day 6 for cost and Schedule? EV PV AC Cost Schedule c. What is the cost variance and schedule variance? d. What is the CPI and SPI? What is the status of the budget and schedule

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cash Flows

Authors: Cyril Joseph

1st Edition

B0B84RHX2D, B0CPV8WDGT

Students also viewed these General Management questions