11. The MOON Construction signed a contract to build a dam over a period of 3 years for a price of P40,000,000. Information relating to
11. The MOON Construction signed a contract to build a dam over a period of 3 years for a price of P40,000,000. Information relating to the performance of the contract is summarized as follows:
2020 2021 2022
Construction costs incurred during the year 8,000,000 16,000,000 24,000,000
Estimated costs to complete 24,000,000 24,000,000 -
Billings during the year 6,000,000 14,000,000 20,000,000
Collections during the year 5,200,000 14,400,000 20,400,000
Computetheprofitorlossforeachyearofthecontractunderthepercentage-of-completionmethod,
and journal entries
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started