11) The project completion time of a project follows normal distribution. If the estimated time along the critical path is 260 days (mean project
11) The project completion time of a project follows normal distribution. If the estimated time along the critical path is 260 days (mean project competition time) and the variance in the project completion time is 81, then a) What is the probability that the project will take 280 days or more to complete? b) What is the probability that the project will take between 240 and 280 days? c) What is the probability that the project will take 250 days or less to complete?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
mean 260 SD Variance 05 8105 9 a When X 280 x Z O z 2802609 222 which gives a value of ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Quantitative Methods For Business
Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam
11th Edition
978-0324651812, 324651813, 978-0324651751
Students also viewed these Finance questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App